The capital city hall received three proposals for the purchase of 20 mini-thermal power plants, which will be located in areas where the heating agent is not supplied in sufficient parameters, and their analysis will take place “as soon as possible”, Nikushor announced on Saturday. Day In essence, this is the purchase of boilers that will heat the water that comes to the heat points below the parameters, so that the hot water is supplied at the required temperature, and they would work from next winter.

Cold radiatorPhoto: Hotnews

According to the mayor, three proposals were submitted for the purchase of 20 mini-thermal power plants, which will be located in areas where the heating agent is not supplied in sufficient parameters, and the stage of analysis of the proposals is currently underway so that the Communal Enterprise Energetica Servicii “determines the winner as soon as possible.”

  • “Thanks to the purchase of 20 modular capacities, we will ensure, starting from the next cold season, optimal supply of heating agent and hot water for 340 blocks with more than 16.3 thousand apartments and approximately 40 thousand tenants from all 6 sectors.
  • The installations will be located in certain heat points located at the ends of the network, where the work was improper and where the heating agent was supplied in insufficient parameters. It is about four thermal points in sector 1, six in sector 2, three other thermal points in sector 3, one in sector 4, three in sector 5 and three more in sector 6,” Nikushor Dan explained.

The value of the contract is estimated at approximately 79 million lei.

According to the feasibility study approved in March 2023 by the General Council, 20 mini-stations will be installed in the following thermal points:

  • PT Radu Beller
  • PT2 Piața Victoriei
  • PT Știrbei Voda
  • PT 4 Aviation
  • PT Ramuri Tay
  • PT 1 Cheile Zănoagei
  • PT 2 Cheile Zănoagei
  • PT 3 Dwarf Keys
  • PT 4 Dwarf Keys
  • PT Luncsoara
  • PT4 Labyrinth
  • PT 1 Labyrinth
  • PT3 Labyrinth
  • PT New Orchard
  • PT9 Mărgeanului
  • PT 10 Mărgeanului
  • PT11 Mărgeanului
  • PT4/10 – Alley of Masters
  • PT7 Virtues
  • PT8 Virtues

According to the indicative schedule in the feasibility study, the systems will be handed over to the beneficiary and put into operation within 30 weeks from the moment the tender is launched. That is, in 7.5 months.

The purchase of these mini-power plants has been under discussion for about 4 years.

In 2022, the capital city hall tried to lease 20 micro power plants for 4 months, but was unsuccessful.

The Lord Mayor said at the time that the rental price was higher than the purchase price because there was a market at the time because we were going through an energy crisis. “Then we did a lease that made the total cost of the lease plus gas lower than the price at which ELCEN was supplying us with the same energy. But no one came to the auction under these conditions,” Nikushor Dan explained.

The cost of the tender for the lease of micro-power plants was 20,668,371 lei.