Traffic on section 3 of the DEx12 Craiova – Pitesti expressway will be opened on Saturday at noon. Approximately 32 kilometers of expressway between Slatina and Koloneşti (border with Arges county) were built by the Romanian company UMB and will be launched shortly before the contract deadline, but with a temporary relief installed at the end from Pitesti.

Expressway DEx12 Kraiova – Pitesti, Lot 3Photo: YouTube recording

Section 3 is approximately 31.7 km long and had an official completion date of January 2024. The new section of the expressway follows section 2 (40 km), also built by UMB and opened last year.

The most sensitive area: the passage to Jitaru / Works until the last moment

The Association Pro Infrastructura recalls that one of the reasons why the opening of traffic on section 3 DEx 12 was made so late in 2023, although forecasts showed that the opening would be possible already in the autumn, is that the CNAIR “unauthorizedly delayed the bureaucratic banality in Jitaru”.

  • “… the Jitaru problem was still being ignored by CNAIR and UMB and it wasn’t until December that everyone panicked. Employees of UMB staged another demonstration khairup, day and night, barely managing to avoid a shameful end. We can only hope that the Jitaru section, which was made on the go in bad weather, will hold up and not need major repairs in the future.
  • All in all, kudos to UMB for sticking to the contract and coat of arms, as a last resort. And finally, congratulations to the CNAIR representatives for finally being able to carry out a temporary relief in Coloniesti, even if it was painful and potentially dangerous, especially in the case of heavy vehicles. I did not predict at the beginning of the year what they will be able to do, well done!” – writes About Infrastructure.

Images from the Jitaru area two days before the inauguration:

VIDEO – What section 3 of the DEx12 expressway Craiova – Pitesti looked like – filming from Slatina to Kolonesti, 10 days before the inauguration:

Expressway Craiova – Pitesti, section 3 – Slatina (Valea Mare) – Kolonesti

Length: 31.75 km

description: 2x(2×3.5) m / Approaches 2×1.5 m / Middle lane 3.00 m

Builder: SA&PE Construct – Spedition UMB – Technotrade

Value: 670 million lei (auction estimate: 999 million lei)

Stadium (December 2023): 94%

Probable completion: December 2023

DEx 12 Craiova – Pitesti – 121 kilometers, with four sections staggered between them

In total, the DEx12 Craiova-Pitesti expressway will be 121 kilometers long, divided into four sections. Now only a third can be used, the rest are in various stages of completion.

In the summer of 2022, the first 40 km of expressway was launched in Romania Section 2 Kraiova-Pitesti expressway.

The plot was built by the association led by the Romanian developer UMB, the same one that is also operating now Section 3and on lot 4 to the junction with the A1 near Pitesti (lot 4 has a completion date of 2024).

Enabled Chapter 1 (17.7 km) 358 million lei contract with the Italians from Tirrena Scavi was terminated in December 2022 at a stage of about 59% due to poor mobilization at the construction site.

For this section, CNAIR concluded a contract for the completion of the section for 440 million lei with the Association OZALTIN ​​​​​​INSAAT TICARET VE SANAYI AS (leader) – STRADE BAUUNTERNEHMUNG SRL – VISIO CONSTRUCTION WORKS SRL. The association assumed that it would complete the work in 18 months.

Work has only recently started, but the minister and highways chiefs are hoping for a record-breaking completion if they announce that it will open in 2024.