Austrian construction company PORR will start work on section 4 of the A1 Sibiu-Pitesti highway in a few weeks, and drilling of one of the longest tunnels on this highway and in Romania is due to begin this year.

Highway A1 Sibiu – Pitesti – five sectionsPhoto: Hotnews

The Austrians from PORR in November 2021 signed a contract worth about 1.7 billion lei for the construction of 9.86 kilometers of motorway between Curtia de Arges and Tigweni – part 4 of the A1 Sibiu – Pitesti. In March 2022, the contractual term of 16 months of design expires, but already now the Minister of Transport declares that the contractor will start work sooner.

  • “They should introduce these weeks for works. They have completed the design phase, they will begin work and Sector 4 will also be attacked,” Sorin announced to Grindeanu on Friday.

In this section, Porr will also have to build a 1,350-meter long tunnel under Momaia Hill, one of the longest tunnels on the A1 highway and practically the first tunnel to be built in Romania.

User “Marinul” from the forum peundemerg.ro, a place that brings together many members of the Pro Infrastructure association, filmed with a drone the route Section 4 Kurtja de Arges – Tigveny and marked on the video the places where all the works of art will be done: bridges, viaducts and Momaya Tunnel.

Sibiu – Pitesti highway, section 4, work on which will begin in 2023

“The video contains an explanation of the 1.35 km long Momai Tunnel and the main bridges/viaducts. Obviously, the location of the structures is approximate/schematic in order to have an idea of ​​the rather high complexity of the route,” reports Pro Infrastructura, which states that on March 16, a construction permit was issued on the site of the village. question.

“According to our information, in the near future the contractor will go to the field, but so far only for the organization of the site and for embankments and structures. We will see traffic in the tunnel no earlier than August,” says API.

“At the moment, the implementation has a deadline of December 2026, counting from the date of issuance of the building permit, but if you take into account the bureaucratic steps and the complexity of the works, it is likely that the opening will be delayed for a long time. 2027, hopefully no later than the summer of 2027,” Pro Infrastructure notes.

Highway A1 Sibiu – Pitesti – Section 4: Tigueni – Curtia de Arges

Length: 9.86 km

PRODUCER: Porr Construct (Austria)

Value: 1,678,873,121.77 lei without VAT.

Contracted: November 2021

Work has begun: March 2022

Contract term: 16 months of design + 44 months of execution

Within the framework of the contract, several works of high complexity will be created, namely:

  • Construction of 12 bridges, crossings and/or viaducts, with an average length of 230 m, of which the longest is Viaduct at km. 84+341, 630m long.
  • Construction of a 1,350 m long tunnel in the Momaya hill crossing area, Argesh county.

Stage of work on each section of the A1 Sibiu – Pitesti highway

The Sibiu-Pitesti motorway will be more than 122 km long and divided into 5 sections, and will connect Central and Western Romania with the European road network, being an important part of the Pan-European Corridor 4.

  • On the A1 Sibiu – Pitesti traffic is opened in December 2022 Chapter 1 (13.17 km from Sibiu to Boita constructor Porr).
  • Currently working on Chapter 5, 30 km from Pitesti to Kurta de Arges (developer Astaldi). Here the builder achieved a physical advance of about 30%.
  • Enabled WITHsection 4 Curtea de Argeș – Tigveni, the Austrians from PORR have currently been working on the design and should start work during 2023.
  • Enabled WITHsection 3 an association of construction workers from Italy and Romania signed in August 2022 the contract for the most expensive motorway tender ever held in Romania.
  • Enabled WITHsection 2, the most difficult section that passes through the Olt Valley and involves the construction of seven tunnels, CNAIR signed an 860 million euro contract with a company from Turkey in February 2022. And here, at the moment, the developer is at the design stage.

Photo: sections on the A1 Sibiu – Pitesti highway

SEE ALSO:

  • OFFICIALLY. Opening date of the Breil/Grindean bridge over the Danube: “I am sending a letter to an Italian colleague to come to the opening”
  • “Unirii” highway: Six proposals from companies from Turkey and Romania for the construction of the first section of the A8 highway